Welcome to our first newsletter update for the work taking place at Glebe House Surgery. So far on site, we have carried out the following works:

– Established the site with Pickerings delivering the offices and welfare units
– Foul drainage has been installed around the new extension
– Surface water drainage is nearing completion
– The Kingspan pump station has been installed
– The Wavin Aquacell soakaway is complete
– The site has been stripped and the reduced level dig is complete
– Works have started on the stone formation level

Over the next two weeks

We will be completing the stoning formation level and progress the foundation works. We will also be diverting the existing drainage system on to the new.