These works are phase 1 of 3 phases planned to reconfigure the Cardiac Catheter Laboratories, including all required ancillary rooms and services. The laboratories will be formed within an existing area within the main theatre block on level D-E of Jubilee Wing. The work will include the replacement of the air handling units, modification to services, electrical, medical gases, cooling and heating to facilitate installation of new single and biplane X-ray equipment.

So far on site, we have:
– Works on level D ceilings and main cables progressed complete 06/10/2020
– Installation of the sub mains cables work has taken place on a night time.
– Stud wall installation setting out and stud works.
– First fix mechanical and electrical services.
– Demolition of ceilings and internal 200mm thick red brick walls are complete.
– Air handling unit 14 and 25 on level D plant room have been stripped out.
– Steel frame 70×70 boxes fitted for the lead-lined doors and screens.
– Screed in works for existing floor trunking and existing walls.

Over the next two weeks

 

  • Continue with first fix mechanical and electrical.
  • New stud walls and lead line works in labs 3 and 4 on level E
  • Continue coordinating with Alison and the team about weekend works for the bin store and storeroom etc. ventilation works.