About the works
We’ve been working hard down on the Level D plant room:
- Removal of the of Air Handling Unit
- Installing the ducting to facilitate the cable pull from Level D to Level E
- Wiring in power back-up systems to support the main switch panel
- Core drilling through nearly half a meter of concrete for the air circulation systems
- Starting to board up partitions on Level E
Over the next two weeks
Over the next two weeks, our focus will be on:
- Building walls
- Continuing to fix up 5.5 tonnes of plasterboard to form Level E partitions
- Carrying on with the cable pull up to, and around Cath Lab 1
- Ensuring the air handling ducting goes in